PACE GK ACADEMY
Login
PACE GK ACADEMY
Home
Past Papers
PPSC Past Papers (Reading)
FPSC Past Papers (Reading)
ITS Past Papers (Reading)
PPSC Past Papers (Quiz)
FPSC Past Papers (Quiz)
ITS Past Papers (Quiz)
Current Affairs
Current Affairs Month Wise
Pak Current Affairs(PACE)
World Current Affairs(PACE)
Pak Current Affairs(PPSC)
World Current Affairs(PPSC)
All-Subjects
Law (FPSC)
General Knowledge (PPSC)
Pakistan Studies (PPSC)
Islamic Studies (PPSC)
World Current Affairs (PPSC)
Pakistan Current Affairs (PPSC)
Mathematics (PPSC)
English (PPSC)
Urdu (PPSC)
Everyday Science (PPSC)
Computer Skills (PPSC)
Geography (PPSC)
Audits & Accounting (PPSC)
Sports (PPSC)
Sociology (PPSC)
Personalities (PPSC)
Current Affairs Month Wise(PACE)
Pakistan Current Affairs(PACE)
World Current Affairs(PACE)
Pedagogy (PACE)
Mock Test
Make Paper
Jobs
Success Stories
35 workers are employed to complete. a construction project in 16 days. Before the project starts, the boss of the company is told that he needs to complete the project in 14 days. Assuming that all the workers work at the same rate, how many more workers does he need to employ in order to complete the project on time?
3
4
5
9
(C)
Leave a Reply
Your email address will not be published. Required fields are marked
Name*
Email*
Your comment here...
Leave a Reply
Your email address will not be published. Required fields are marked